$19.9 million during the years ended December 31, 2017, 2016 and 2015, respectively, and are reported as cost of operations - affiliate in the consolidated statements of operations. Amounts incurred for O&M and asset management services from SunEdison subsequent to the Merger closing date on October 16, 2017 are included within cost of operations in the consolidated statement of operations since SunEdison was no longer an affiliate of the Company.

In addition, in conjunction with the First Wind Acquisition in 2015, SunEdison committed to reimburse the Company for capital expenditures and O&M labor fees in excess of budgeted amounts (not to exceed $53.9 million through 2019) for certain of its wind power plants. During the year ended December 31, 2015, the Company received contributions pursuant to this agreement of $4.3 million. The total amount related to capital expenditures of $50.0 million was initially recognized in renewable energy facilities as a prepaid warranty as the amount was part of the consideration paid on the acquisition date. As a result of the SunEdison Bankruptcy, the Company recorded a loss of $45.4 million during the year ended December 31, 2015 related to the write-off of the remaining balance of the prepaid warranty, which was net of depreciation expense of $1.9 million and capital expenditure reimbursements received of $2.7 million, and is reported as loss on prepaid warranty - affiliate in the consolidated statement of operations. As a result of the SunEdison Bankruptcy, no contributions were received during 2016 or 2017.

Historical Engineering, Procurement and Construction Contracts and Module Warranties

SunEdison served as the prime construction contractor for most of the Company's renewable energy facilities acquired from SunEdison pursuant to engineering, procurement and construction contracts with the Company's project-level subsidiaries. The Company also generally obtained solar module warranties from SunEdison, including workmanship warranties and output guarantees, for those solar facilities that the Company acquired from SunEdison that utilized SunEdison modules. Third party insurance was procured by SunEdison to back-stop payment of warranty claims for SunEdison modules purchased from January of 2011 through January of 2017.

During the first quarter of 2017, the Company received $7.0 million from SunEdison in satisfaction of outstanding claims made under engineering, procurement and construction contracts, of which $4.8 million related to the Company's renewable energy facility located in Chile and compensated the relevant project company as the facility's performance during the warranty period was below that guaranteed by an affiliate of SunEdison under the applicable EPC contract. These receipts were treated as equity contributions from SunEdison within Net SunEdison investment on the consolidated statement of stockholders' equity for the year ended December 31, 2017. As discussed above, pursuant to the Settlement Agreement entered into with SunEdison, and upon the consummation of the Merger with affiliates of Brookfield on October 16, 2017, these construction and related contracts were rejected without further liability, claims or damages on the part of the Company.

Historical Interest Payment Agreement with SunEdison

Since the Company's initial public offering (“IPO”) on July 23, 2014, the Company was a party to an interest payment agreement with SunEdison, pursuant to which SunEdison would pay a portion of the scheduled interest payments on certain corporate-level indebtedness. The Company received equity contributions totaling $8.0 million and $10.6 million from SunEdison pursuant to this agreement during the years ended December 31, 2016 and 2015, respectively. The 2016 contribution was received in the first quarter of 2016 and accrued for during fiscal 2015. As of the first quarter of 2016, the Company had received a cumulative amount of $24.0 million under this agreement from SunEdison with $24.0 million of scheduled payments due in future periods. The Company did not receive any payments from SunEdison pursuant to this agreement subsequent to the first quarter of 2016. As discussed above, pursuant to the Settlement Agreement entered into with SunEdison, and upon the consummation of the Merger with affiliates of Brookfield on October 16, 2017, this agreement was rejected without further liability, claims or damages on the part of the Company.

Historical Support Agreement and Intercompany Agreement with SunEdison

The Company entered into a project support agreement with SunEdison (the “Support Agreement”) on July 23, 2014, which provided the Company the option to purchase additional renewable energy facilities from SunEdison and also provided the Company a right of first offer with respect to certain other renewable energy facilities. During the years ended December 31, 2016 and 2015, the Company acquired renewable energy facilities with a combined nameplate capacity of 19.2 MW and 350.9 MW, respectively, from SunEdison under the Support Agreement (see Note 3. Transactions Between Entities Under Common Control). The Company did not acquire any renewable energy facilities from SunEdison under the Support Agreement during the year ended December 31, 2017.


144